| Angel Place, Office Tower
Required a Sheetmetal finish to all fire rated Plant Room Ductwork
sections below 2.2m height, in order to meet Contract / Consultant
specification requirements for hardness.
|
Proposed, designed and installed a mechanically reinforced Hard-Coat
system, incorporating our Vermitex ‘7’ cement based
compound, applied to an LAF expanded metal construction installed
to Vermiduct
Benefit:
A cost effective and timely alternative to Sheetmetal was offered.
|
 |
| Angel Place, Office Tower
Required an aesthetic and cost effective alternative to 3 sided
exposure SPF ductwork within plant room fire corridor.
|
Proposed and installed our Trimesh® – Vermiduct Bulkhead system
to underside of ductwork (1-sided => reduced surface area) providing
an aesthetic, textured spray finish with radius turndown at masonry
blockwork.
Benefit:
A cost effective solution alternative to fire rating a 3 sided
ductwork arrangement
|
 |
| Angel Place, Recital Hall Required
a lightweight and cost effective alternative to a complex fire rated
sheet metal car park exhaust plenum construction.
|
Proposed, designed and installed our Trimesh® – Vermiduct
fire rated plenum to underside of concrete soffit.
Design: The Trimesh® construction
was suspended from the slab above via fire engineered hanging rods
& furring channel arrangements (doubling as fixing centres for
suspended ceiling and essential services installation below by others).
Plenum was fixed at masonry wall and slab via flexible joints (for
improved vibration resistance). Trimesh® panels were sheetmetal backed
to ensure airtight seal to exhaust air.
Benefit:
A cost effective, lightweight and air tight construction solution.
|

 |
| Westmead Hosiptal Required the
use of PVC for the Laboratories Fume Cabinets within the Hospital
to avoid erosion from toxic gases and chemicals
|
LAF specifically researched and designed a 2-Hour system for the
Fume Cabinets and relevant supports to the underside of the metal
deck roof.
Benefit:
The system provided a cost-effective alternative to Stainless Steel.
|
 |
| GPO During the Construction
of the Substation Risers it was discovered that the Risers would
not meet the specified requirements of the Sydney County Council
on Fire Rating or the Cross Sectional area of the ductwork.
|
LAF proposed that the Risers be constructed out of Trimesh® that
would provide a 3 hour FRL and accommodate the specified cross sectional
area.
Benefit:
The System avoided the variation to masonry walls and extensive
programme delays. It also proved to be far more economical than
Sheetmetal construction.
|

 |
| MUA Required a 2 Way
Fire Rated Ceiling System. The original system had been engineered
to incorporate Structural Steel Beams that would impose a heavy
load onto the concrete platt seating
|
Proposed, designed and installed a lightweight 2 Way Fire Rated
Plenum using our specifically designed Trimesh® System.
Benefit:
This system was to reduce the cost and time involved incorporating
the additional steelwork and plasterboard construction.
|
 |