Reinforcing Mesh
(Interior & Exterior Reinforcement Applications)
Product Description
The Trimesh® panel is a lightweight
construction system which can be used for erecting non-loadbearing elements
such as mono or multilayered horizontal and vertical barriers as well
as complementary structures such as risers dividing walls, internal curtain
walls, thermal Insulation walls and floors.
The Trimesh® panel is a spatial frame manufactured from an electrically
welded high tensile steel wire of 2 mm diameter. The base panel has a
rigid three-dimensional structure which can either be sprayed on site,
or factory pre-cast to provide a monolithic base. The Trimesh® panel
can also be lined on one side with a layer of aluminium foil that acts
as a type of ‘form work’ to compliment the spray application.
To achieve the superior Fire and Acoustic levels outlined in our test
data, the Trimesh® base must be sprayed with the LAF Group complementary
products. (1)
The final product is a panel with two layers of mesh with diagonal stiffeners,
sprayed with variable material thickness. The adopted final thickness
will depend on the Fire Resistance Level (FRL), Sound Transmission Class
(STC) Rating or Loading that is required.
The Trimesh® panels are installed with the framing first and then
with the joints lapped by joiner strips, in accordance with the adopted
LAF methodology. Once fixed, the Trimesh® panel is ready to be sprayed
in two stages. The first stage is spraying up to the mesh. Some mesh is
left exposed to provide satisfactory keying of subsequent coats. The second
stage or final coat is then applied to the required thickness. When included
the aluminium foil provides a backing for the spray application, and acts
as a reflective thermal vapour barrier. The system complies with the requirements
set out in the various Standards. In some circumstances the Trimesh®
can be "cast-in" between layers of form work in accordance with
normal concrete wall construction practice.
Standards & Guideline References
When constructing special structures that
fall outside of the LAF tested prototype and spans, it is important that
reference be made to the applicable Standards and guidelines. Alternatively,
a practising Structural Engineer may review the design parameters and
provide conforming certification.
Materials
The various mortars should be applied by
means of Mechanical Spray equipment. LAF have tested the Trimesh®
system in conjunction with various mortars: Alltex® and Vermiduct®
are the most commonly used. The decision on which product best suites
the application is to be made by the Specifier taking into account the
following characteristics:
- Hardness of Surface
- Quality of finish
- Fire Resistance Level to be achieved
- Space available for construction of the barrier
- Engineering requirements (Design Load; Span, Height & Width
limitations etc)
Additional Reinforcement
Additional reinforcement can be introduced
in the form of standard deformed reinforcing bars, which must be installed
in accordance with the relevant Standards and Codes.
Water-Cement Ratio
As with all cement based mortars, reducing
or minimising the amount of water used in the mixing of the compound is
imperative. Excess water should be avoided as this water will tend to
‘weep’ out of the mortar and contribute to the formation of
small fissures as well as gaps. This will inevitably compound the degradation
of the concrete mix.
A low slump mix will provide better adhesion onto the wall especially
during the second application, and save Labour. This means there will
be less material run-off.
Drying Shrinkage
The drying shrinkage phenomenon arises from
the contraction in volume as a consequence of the evaporation of the interstitial
water. The phenomenon affects all concrete structures but, in particular
those with reduced thickness as the evaporation surface ratio is much
greater compared to the mass of the wall.
This phenomenon can be reduced as follows:
- In some circumstances the use of man made fibres may
reduce cracking as well as increase the abrasion resistance of the final
product.
- Maintain relatively good ambience humidity. Wetting the
finished product is good practice.
- Protect the finished product from excessive quick drying
Installation Methodology
Foundation
Where necessary, the specifier/designer
may call for suitably constructed foundations with the inclusion of starter
bars at specified centres. The starter bars may then simply be inserted
into the holes previously drilled into the concrete slab. As the Trimesh®
panel is inserted over these starter bars, the correct location is of
paramount importance.
Vertical element erection
The operation simply consists in the placing
of the Trimesh® panels over the foundations or slab and subsequently
tying the Trimesh® back to the starter bars or in some instances,
clipping the panel with a pneumatic crimping tool.
To ensure that the panels are plumb and square, temporary propping and
bracing is recommended.
Caution:
- Check the location of any openings to ensure the
correct sequential programming for cutting openings into the Trimesh®
panels using an angle grinder, side cutters or nippers.
- Check if additional reinforcement is to be located within
the Trimesh® panel before they are secured to the starter bars.
On completion of the dry panel
erection:
- Install fixtures at openings (windows and door frames
etc.).
- Install electrical and plumbing services.
- Ensure that the Trimesh® structural integrity and
continuity is maintained by installing joining strips at all vertical
joints and securing these in place by means of pneumatically fixed steel
rings.
- Organise typical reinforcement nodes as per the manufacturer’s
details.
- Repair Trimesh® at electrical and plumbing
services installation.
NOTE: It is good practice to ensure
that services do not travel horizontally for long distances. This reduces
the risk of compromising the wall’s structural stability. Always
ensure that any services ‘chased’ within the wall are rendered
over with mortar satisfactorily.
Horizontal element erection
Generally installation will be in accordance
with the traditional methods of a concrete slab construction. Suspended
horizontal Trimesh® installations, such as plenum enclosures etc.,
can be suspended from hanging rods which are installed at the correct
locations in conjunction with other suspension systems, such as Unistrut,
to carry services. Where a perimeter masonry element is available, the
Trimesh® may be wire tied to previously installed dowels or in some
instances, or clipping the panel with a pneumatic crimping tool.
Caution:
- It is good practice to install a positioning angle to
act as a reference guide and connection between the wall panel and the
horizontal element at the ‘head’ of the horizontal Trimesh
being installed.
When building a multi-layered element, ensure that the starter bars
for the next wall section have been installed, that all the services
have been installed, and that all the required reinforcement is located
correctly and will be covered with the correct thickness of mortar prior
to spraying.
On completion of the dry panel erection:
- Install fixtures at openings (eg Access Panels, Light
Boxes etc.).
- Install electrical and plumbing services.
- Ensure that the Trimesh® structural
integrity and continuity is maintained by installing joining strips
at all horizontal joints and securing these in place by means of pneumatically
fixed steel rings.
- Organise typical reinforcement nodes as per the manufacturer’s
details.
- Repair Trimesh® at electrical and plumbing
services installation.
Mortar Spraying
Vertical elements
After having ensured that the correct spray
compound is being used and that the walls are plumb, the mechanical spray
plastering operations may commence.
- Spray first coat to partially cover the mesh, then
level.
- Provide a scratch coat to ensure a subsequent and
superior bond.
- Position levelling screeds at the required centres.
- Apply a second coat, until the required thickness
is achieved
- Trowel or Wood float as may be necessary.
- Where required, apply a finishing coat.
Horizontal Elements
Again, check that the correct materials
have been prepared for spraying. The slab should only be sprayed after
the vertical elements have been completed and the proper reinforcement
has been installed.
If using the foil-backed Trimesh®, caution should be exercised when
spraying to avoid overloading of the aluminium foil as the ‘wet
weight’ of the spray compound can tear the foil, when located on
the lower side (i.e. spraying from above).
- Spray first coat to partially cover the mesh,
then level
- Provide a scratch coat to ensure a subsequent
and superior bond
- Position levelling screeds at the required centres
- Apply a second coat, until the required thickness
is achieved
- Trowel or Wood float as may be necessary
- Where required, apply finishing coat
Caution:
- Continuously ensure that the flow characteristics
of the material are correct to avoid hose blockages.
- The use of leaky hoses should be avoided, as water
loss at the hose joints will contribute to blockages.
- Keep the walls humid to reduce ‘Drying
Shrinkage’.
Corrosion prevention
In high humidity and in wet areas spray
materials should not be relied upon as a rust preventative coating. Vermitex®
materials are porous and will allow the passage of moisture through to
the substrate. If a concern exists about moisture levels, the spray material
may have to be top coated with an appropriate membrane coating. (1)
Note that in some circumstances the Trimesh® may cause ‘galvanic
reactions’ when in contact with particular metals, and suitable
preparation work may be required. (1)
The Trimesh® structural solution is a monolithic box type with a static
behaviour similar to that of masonry load bearing walls, or to that of
large precast panels. The Trimesh® panel system may be employed in
wall construction and be suspended from any superimposed (eg Concrete
Slab, Beams etc.) element to circumvent the slenderness ratio conditions
imposed by some of the Standards.
Trimesh® is available in the following sizes: (Note: H = Distance
between the two layers of mesh)
| |
(mm) |
|
(mm) |
| Height (h) |
30, 50, 75, 100, 125
and 150 |
Width (w) |
1,210 |
| |
|
|
|
| Panel Length |
Lmax |
Optimal wire diameter |
Longitude |
Transverse |
Diagonal |
| |
6000 mm |
|
(mm) |
(mm) |
(mm) |
| Wire Specification |
Number of wires |
Diameter (mm) |
H30; H50; H75 |
2 Ø |
2 Ø |
2 Ø |
| Diagonal |
nº 266 (per m²) |
2 to 3 Ø |
H100 |
3 Ø |
2 Ø |
2 Ø |
| Longitudinal |
nº 40 (over 1.2 Lm) |
2 to 5 Ø |
H125 |
2 to 5 Ø |
2 Ø |
2 Ø |
| Cross |
nº 31.6 (over 1 Lm) |
2 to 3 Ø |
H150 |
3 to 5 Ø |
3 Ø |
3 Ø |
| Polystyrene Density |
32 kg/m³ |
|
Trimesh®
Density (H30) |
1.86 kg/m² |
|
|
| Optimal Insulation |
Polystyrene core (mm) |
Wall Thickness (mm) |
Allowed
Allowed modifications |
| H30 |
nil |
40 - 50 |
Eliminate some trusses |
| H50 |
25 to 30 |
75 |
Eliminate diagonals
(max 70%) |
| H75 |
35 to 45 |
100 |
Eliminate upper transversal
wires |
| H100 |
45 to 55 |
140 |
|
| H125 |
55 to 65 |
175 |
|
| H150 |
65 to 75 |
200 |
|
Note: The thickness
and weight of the panels will vary proportionally with the overall applied
thickness of Mortar. (1)
Health Statement
Trimesh® contains no asbestos and presents
no known health hazard before, during and after application. Normal precautions
relevant to the handling of gypsum products apply: dust mask, eye protection
and covering of sensitive skin.
NOTES:
1. Refer to LAF for further detail and information.
2. Refer to L & A Fazzini Manufacturing Pty Ltd for additional information
on applicable thickness of spray cover to reinforcing bars.
For more information or MSDS on Vermitex®
‘AF’ or any other products,
please see the technical
data page, or contact: L & A Fazzini
Manufacturing Pty Ltd
|